Final text for the XXth Quarterly Report is due ddd DD MMMM YYYY
This is the report for the end of the XX period (months #-#).
Link to the Deliverables Table
Deliverables due during the XX reporting quarter:
| D# | Month Due |
|---|---|
| D8.02 Hardware design document for simultaneous I/O storage elements (AALTO) | 8 |
| D2.01 EVN-NREN meeting 1 | 9 |
| D4.06 Publish Print Items (see section “2011 March Brochure ”) | 9 |
| D5.04 Automated job scheduling | 9 |
The following deliverables were submitted to and their receipt acknowledged by the Commission during this quarter:
| Deliverable Number and Description | confirmed on 1) |
|---|---|
| D5.2 Metrics, selection criteria and user feedback | 11 Jan 2011 |
| D7.1 Workflow Manager requirements from telescope operators | 04 Jan 2011 |
| D7.2 Workflow Manager requirements from correlator operators | 25 Jan 2011 |
| D8.1 Interface design document of storage element API | 25 Jan 2011 |
| D8.2 Hardware design document for simultaneous I/O storage elements | 8 Mar 2011 |