!!! DRAFT !!!

This is a DRAFT version of the revised deliverables table. This draft includes the updates presented at the First Annual Review. There are still some checks that need to be run to make sure that all the information from the previous table was correctly integrated into this new table. – tcy, 2007 may 16

D#LeadAD#Deliverable DescriptionPlannedActualStatusNature DisLev
D1 NA4 NA4.01 Creation of Public EXPReS web-site 2 1 4 O PU
D2 JRA1 J1.1 Data acquisition requirements document 2 3 4 R PU
D3 JRA1 J1.2 Protocols strategic document 2 2 4 R PU
D4 NA2 NA2.01 EVN-NREN meeting No. 1 (under auspices of EXPReS) (minutes) 3 6 4 R PP
D5 SA1 SA1.1 Central data link control, Correlator Control Code modifications (not documented) 3 7 4 D PU
D6 NA3 NA3.1 First meeting of eVSAG under auspices of EXPReS (minutes) 4 9 4 R PP
D7 NA4 NA4.02 Creation of EXPReS web-based management tools 4 4 4 O PP
D8 JRA1 J1.3 Visualization software 4 P PU
D9 JRA1 J1.4 Correlator design specification 1) 5 3 R PU
D10 NA4 NA4.03 Generation of PR material (phase 1: logos and posters, PowerPoint template, press releases and news clippings, brochure) 6 1 x O PU
D13 SA2 SA2.01 Feasibility study (via protected link) of the last-mile connection to the nearest NREN node for participant CNIG-IGN 6 9 4 R PU
D14 SA2 SA2.02 Feasibility study (via protected link) of the last-mile connection to the nearest NREN node for participant MPIfR 6 9 4 R PU
D15 SA2 SA2.03 Equipment of the last-mile infrastructure for participant INAF (telescope in Medicina) (via protected link) 6 9 4 O PU
D16 SA2 SA2.04 Feasibility study (via protected link) of the last-mile connections to the nearest GEANT NREN node for participant CAS (Shanghai, Urumqi, Miyun, Yunnan ) 6 9 4 R PU
D17 SA2 SA2.05 Feasibility study (via protected link) of the last-mile connection to the nearest NREN node for participant VIRAC 6 9 4 R PU
D18 SA2 SA2.06 Feasibility study (via protected link) of the last-mile connection to the nearest NREN node for participant HRAO 6 9 4 R PU
D19 SA2 SA2.07 Feasibility study (via protected link) of the last-mile connection to the nearest NREN node for participant NAIC (Arecibo) 6 9 4 R PU
D20 SA2 SA2.08 Feasibility study (via protected link) of the last-mile connection to the nearest NREN node for participant TIGO 6 9 4 R PU
D21 SA2 SA2.09 Feasibility study (via protected link) of the last-mile connection to AARNET for participant CSIRO 6 9 4 R PU
D22 JRA1 J1.5 Overall design document 6 0 R PU
D23 JRA1 J1.6 eVLBI-Grid design document 6 9 4 R PU
D24 JRA1 J1.7 eVLBI fringes PC-EVN (Month 7 Demo report) 7 7 4 D PU
D25 JRA1 J1.8 LOFAR connection strategic document 7 11 4 R PU
D26 JRA1 J1.9 Data acquisition design document 8 11 4 R PU
D29 SA2 SA2.10 e-VLBI test observations, Medicina (256 Mbps fringes) (science announcement) 10 3 4 D PU
D30 JRA1 J1.10 eVLBI-Grid interface document 10 10 4 R PU
D119 MRO SA2.11 Equipment of the last-mile infrastructure for participant MRO 12 ongoing O PU
D120 CNIG-IGN SA2.12 Construction and equipment of the last-mile infrastructure for participant CNIG-IGN 12 ongoing R PU
D121 MPIfR SA2.13 Construction and equipment of the last-mile infrastructure for participant MPIfR 12 ongoing
D32 NA1 NA1.01 Annual report (incl. Financial information) to EC 12
D33 NA2 NA2.02 NA2 annual report No. 1 (as part of EXPReS Ann. Rep No. 1) 12 R PP
D34 NA4 NA4.04 e-VLBI Demonstration and attendance at Network events (events, presentations) 12 12 x R PP
D35 SA1 SA1.5 Network Protocol decision: A Simulation model for e-VLBI traffic on network links in the Netherlands,Comparing Simulation and Network Monitoring Results, On Network Monitoring of end-to-end paths used for e-VLBI, UDP-like TCP 12 2 O PU
D37 SA2 SA2.011 Equipment of the last-mile infrastructure for participant MRO 12 5 4 D PU
D38 SA2 SA2.12 Construction and equipment of the last-mile infrastructure for participant CNIG-IGN 12 O PU
D39 SA2 SA2.13 Construction and equipment of the last-mile infrastructure for participant MPIfR 12 O PU
D40 SA1 SA1.8 Monitoring processes 12 7 4 O PU
D122 JBO DJ1.11a Interim Protocols performance report 13
D123 JIVE DJ1.4 Correlator design specification 13
D41 JBO J1.11 Protocols performance report 13
D42 JIVE J1.12 Software correlator core 15 R PU
D44 SA1 SA1.10 Real-time data processor control software (no document) 15 4 4 P PU
D11 JIVE SA1.2 Job preparation utilities 16 2 D PU
D124 JIVE SA1.22 Mark5 hardware upgrade 16
D28 JIVE SA1.5 Network protocol decision 16 2 P PU
D46 OSO NA3.2 eVSAG meeting No. 2 16 D PU
D47 SA1 SA1.11 Real-time Pipeline 16 9 4 R PP
D125 JIVE DJ1.5 Overall design document 17
D126 JIVE SA1.23 Use of WSRT synthesis data for e-VLBI calibration 17
D127 O/S SA1.24 Mark5A code modifications 17
D128 O/S SA1.25 Mark5B code modifications 17
D43 JIVE J1.13 Software data product 17 P PU
D95 O/S SA1.20 Improved network applications 17 P PU
D129 HRAO SA2.06 Feasibility study of the last-mile connection to the nearest NREN node for participant HRAO 18 ongoing
D130 MERLIN, JIVE SA2.14 10 Gbps link upgrade between MERLIN and JIVE 18 pendent
D131 MRO SA2.15 e-VLBI test observations, Metsähovi 18 13
D132 AARNET, CSIRO SA2.17 Construction and equipment of the last-mile infrastructure in AARNET to allow connection of participant CSIRO 18
D133 VIRAC SA2.21 Construction and equipment of the last-mile infrastructure for participant VIRAC 18
D134 TIGO SA2.23 Construction and equipment of the last-mile infrastructure for participant TIGO 18
D135 AARNET SA2.24 AARNET connectivity enhancements 18
D48 JIVE NA2.03 EVN-NREN meeting No. 2 18 D PU
D49 JBO NA4.05 Generation of new PR material (phase 2) 18 R PP
D50 SA1 SA1.12 Visibility monitor 18 4 4 O PU
D51 JIVE SA1.13 Tested software for operational improvements 18 D PU
D55 SA2 SA2.14 10 Gbps link upgrade between MERLIN and JIVE 18 D PU
D56 SA2 SA2.15 e-VLBI test observations, Metsahovi 18 13 4 O PU
D57 SA2 SA2.16 Construction and equipment of the last-mile infrastructure for participant Shanghai 18 R PU
D58 SA2 SA2.17 Construction and equipment of the last-mile infrastructure in AARNET to allow connection of participant CSIRO 18 O PU
D59 SA2 SA2.18 Construction and equipment of the last-mile infrastructure for participant Urumqi 18 O PU
D60 SA2 SA2.19 Construction and equipment of the last-mile infrastructure for participant Miyun 18 O PU
D61 SA2 SA2.20 Construction and equipment of the last-mile infrastructure for participant Kunming 18 O PU
D62 SA2 SA2.21 Construction and equipment of the last-mile infrastructure for participant VIRAC 18 O PU
D63 SA2 SA2.22 Equipment of the last-mile infrastructure for participant NAIC 18 O PU
D64 SA2 SA2.23 Construction and equipment of the last-mile infrastructure for participant TIGO 18 O PU
D65 SA2 SA2.24 AARNET connectivity enhancements 18 O PU
D68 PSNC J1.16 Software for workflow management 18 R PU
D71 JIVE SA1.17 Flexible local GE network 18 1 O PU
D136 JIVE SA1.26 Investigating a 1024M sub-array 20
D137 INAF SA2.25 Feasibility study of the last-mile connection to the nearest GÉANT node for participant INAF (Sardinia) 20
D138 UniMan, OSO SA2.26 10 Gbps link between UniMan and OSO for ultra-VLBI tests 20
D69 SA2 SA2.25 Feasibility study of the last-mile connection to the nearest GÉANT node for participant INAF (Sardinia) 20 P PU
D70 SA2 SA2.26 10 Gbps link between UniMan and OSO for ultra-VLBI tests 20 R PU
D139 JIVE DJ1.3 Visualization software 21
D140 ShAO SA2.16 Construction and equipment of the last-mile infrastructure for participant Shanghai 21
D141 ShAO SA2.18 Construction and equipment of the last-mile infrastructure for participant Urumqi 21
D142 ShAO SA2.19 Construction and equipment of the last-mile infrastructure for participant Miyun 21
D143 ShAO SA2.20 Construction and equipment of the last-mile infrastructure for participant Kunming 21
D144 MPIfR SA2.27 e-VLBI test observations, Effelsberg 21
D67 ASTRON J1.15 LOFAR station interface report 21 R PU
D72 SA2 SA2.27 e-VLBI test observations, Effelsberg 21 D PU
D145 MRO, CSIRO SA2.28 e-VLBI test observations, Metsahovi / CSIRO 22
D146 OAN SA2.29 e-VLBI test observations, Yebes 22
D45 UniMan SA1.9 Tests using local Jodrell Bank home e-MERLIN telescope 22 P PU
D66 MPI J1.14 Data acquisition interface document 22 O PU
D73 SA2 SA2.28 e-VLBI test observations, Metsahovi 22 R PU
D74 SA2 SA2.29 e-VLBI test observations, Yebes 22 R PU
D54 JIVE SA1.15 VSI Interfaces 23 D PU
D75 JIVE J1.17 Software for correlation on cluster 23 R PU
D79 JIVE J1.21 Software cluster correlation 23 D PU
D80 JIVE J1.22 First fringes software correlator 23 P PU
D147 NAIC SA2.22 Equipment of the last-mile infrastructure for participant NAIC 24
D31 DANTE NA2.04 NA2 annual report No. 2 (as part of EXPReS Ann. Rep No. 2) 24 R PU
D52 UniMan SA1.14 Test using remote e-MERLIN telescope 24 D PU
D81 JIVE NA1.02 Annual report (incl. Financial information) to EC 24 D PU
D83 JIVE NA4.06 e-VLBI Demonstration and attendance at Network events. 24 R PP
D85 UniMan SA1.19 Multiple e-MERLIN telescope tests 24 D PU
D53 JIVE SA1.16 VSI support software 26 D PU
D76 MPI J1.18 Data acquisition test report 26 P PU
D77 MRO/OSO J1.19 Data acquisition prototype at telescope 26 R PU
D88 DANTE NA2.05 EVN-NREN meeting No. 3 26 O PU
D89 DANTE NA2.06 EVN-NREN representatives present EXPReS networking results at the e-VLBI Science & Technology Workshop 26 P PU
D91 OSO NA3.3 eVSAG meeting No. 3 26 R PU
D148 JIVE SA1.27 Space craft tracking correlator mode 27
D149 HRAO SA2.30 Construction and equipment of the last-mile infrastructure for participant HartRAO 27
D12 JIVE SA1.3 Fast/adaptive scheduling tools 28 1 D PU
D150 JBO DJ1.11b Final Protocols performance report 28
D151 JIVE SA1.28 On-the-fly fringe fitting 28
D93 PSNC J1.25 Software routing 29 R PP
D100 SA2 SA2.34 e-VLBI test observations, VIRAC 30 R PU
D101 SA2 SA2.35 e-VLBI test observations, HRAO 30 R PU
D102 SA2 SA2.36 e-VLBI test observations, NAIC, Arecibo 30 R PU
D103 SA2 SA2.37 e-VLBI test observations, TIGO 30 R PU
D104 SA2 SA2.38 Construction and equipment of the last-mile infrastructure for participant INAF (Sardinia) 30 R PU
D105 JBO J1.26 eMERLIN interface available 30 R PU
D152 JIVE SA1.29 Real-time download and extraction of station information 30
D153 VIRAC SA2.34 e-VLBI test observations, VIRAC 30
D154 TIGO SA2.37 e-VLBI test observations, TIGO 30
D155 INAF SA2.38 Construction and equipment of the last-mile infrastructure for participant INAF (Sardinia) 30
D84 JIVE SA1.18 Network monitoring tools 30 O PU
D87 JIVE J1.23 Software to collect distributed output 30 D PU
D96 SA1 SA1.21 Monitoring user interfaces 30 7 4 O PU
D97 SA2 SA2.31 e-VLBI test observations, Urunqi 30 D PU
D98 SA2 SA2.32 e-VLBI test observations, Mijun 30 D PU
D99 SA2 SA2.33 e-VLBI test observations, Kunming 30 R PU
D106 JIVE J1.27 Fringes with new routing 31 O PU
D92 JIVE J1.24 Software to create data product from distributed correlation 31
D94 OSO NA3.4 e-VLBI Workshop held in Onsala 31 P PU
D107 OSO NA3.5 Publication of e-VLBI Workshop proceedings 32 P PU
D108 JIVE J1.28 Software distributed correlation 33 D PU
D156 JIVE SA1.30 Automated correlator diagnostics 33
D157 ShAO SA2.31 e-VLBI test observations, Urunqi 33
D158 ShAO SA2.32 e-VLBI test observations, Mijun 33
D159 ShAO SA2.33 e-VLBI test observations, Kunming 33
D160 HRAO SA2.35 e-VLBI test observations, HRAO 33
D78 OSO J1.20 Overall broadband demonstration 33 P PU
D109 JIVE J1.29 First fringes Grid correlator 34 R PU
D161 JIVE SA1.31 Removing/adding stations from the correlation process on the fly 34
D110 JIVE J1.30 First fringes on FABRIC 35 P PU
D111 JIVE NA1.03 Annual report (incl. Financial information) to EC 36 D PU
D112 JIVE NA1.04 Final Report to Board and EC 36 D PU
D113 JIVE NA1.05 Final Plan for using and disseminating knowledge 36 R PP
D114 JIVE NA1.06 Implementation of the Gender Action Plan 36 R PP
D115 JIVE NA1.07 Raising public participation and awareness 36 R PP
D116 JIVE NA2.07 NA2 annual & Final reports 36 R PP
D117 JIVE NA4.07 e-VLBI Demonstration and attendance at network events. 36 R PU
D118 JIVE J1.31 Final report 36 R PP
D162 JIVE SA1.32 Enhancements & additions to real-time pipeline 36
D163 JIVE SA1.33 Enhancements & additions to existing monitoring tools 36
D164 NAIC SA2.36 e-VLBI test observations, NAIC, Arecibo 36
D36 JIVE SA1.7 Monitored information handling modules 36 D PU
D82 DANTE NA2.08 NA2 annual report No. 3 (as part of EXPReS Ann. Rep No. 3) 36 R PP
D90 DANTE NA2.09 EVN-NREN meeting n/a n/a n/a
expres/management/deliverablesperiod2.txt · Last modified: 2007/06/12 13:03 by 127.0.0.1